Planning an extension: what actually happens, in order.

Most of the stress in an extension comes from not knowing what the next step is or who is responsible for it. This is the whole sequence in plain English — the permissions, the notices, the structure and the order the trades run in — written so you can hold any builder to it, not just us.

General guidance, not a substitute for advice on your specific property. Permitted development rights and party wall obligations depend on the individual house, and we will go through yours at the first visit.

01

Decide what the extension is for before you decide how big it is

Almost every extension brief starts with a size and works backwards. It is the wrong way round. The useful question is what the room has to do — cook, eat, work, hold a sofa, catch the afternoon sun — because that determines the shape, the glazing orientation and where the doors go far more than the square metres do.

It also decides how the rest of the house works afterwards. The commonest regret on a single-storey rear extension is not that it was too small; it is that the original back room became a dark corridor to it.

Worth knowing

Before you get drawings, stand in the garden at the time of day you would actually use the room and look at where the light comes from.

02

Permitted development or a planning application

Many single-storey rear extensions on houses fall under permitted development rights, which means no planning application — but the rights come with limits on depth, height, eaves height, materials and how much of the garden is built on, and they are narrower on a semi than a detached, narrower again if the house has already been extended, and narrower still in a conservation area or on a listed building.

Chester has a lot of all three. If the house is in a conservation area, or is listed, or has had permitted development rights removed by an Article 4 direction, the calculation changes completely. And permitted development is not a nothing-to-do route either — a Lawful Development Certificate is worth having, because it is the piece of paper a buyer’s solicitor will ask for in ten years’ time.

Worth knowing

Permitted development is a right, not an approval. Nobody checks it until you sell — which is exactly why you want the certificate.

03

Building regulations are a separate thing entirely

Planning permission is about whether you may build it. Building control is about whether it is built properly — foundations, structure, insulation, fire safety, ventilation, drainage, glazing and electrical work. An extension needs building regulations approval whether or not it needed planning permission. The two are unrelated and people conflate them constantly.

In practice that means inspections at set stages: foundations before they are covered, damp-proof course and oversite, structural elements, insulation, drainage before it is backfilled, and completion. Missing an inspection is expensive, because the only remedy is opening the work up again.

Worth knowing

Build the inspection stages into the programme at the start. A foundation that is poured before it is inspected is a foundation that may have to be dug out.

04

Neighbours, boundaries and the Party Wall etc. Act

If you are excavating within three metres of a neighbour’s structure and deeper than their foundations, building on the line of junction, or cutting into a shared wall, the Party Wall etc. Act 1996 applies and notices have to be served — usually two months before work starts on a party wall, one month for excavation and line-of-junction work.

It is not a hostile process and it is not optional. Served early and explained properly, most neighbours simply consent. Served late, or not at all, it becomes the single most effective way to stop a job dead.

Worth knowing

On a terrace or a semi this is almost always relevant. Deal with it at drawing stage, not the week the digger arrives.

05

Structure: the part that decides the whole programme

Where the new extension meets the old house, something has to carry the wall you are removing. That means a steel beam sized by a structural engineer, temporary props and needles while the opening is formed, and padstones that can actually take the load at each end.

This is the first heavy stage and everything downstream waits on it — you cannot board, plaster, run services or set out a kitchen until the opening is formed and the structure is permanent. Get the opening width settled at this point, with the finished room in mind, because widening it later means doing the whole thing twice.

Worth knowing

Agree the exact finished opening dimensions before the steel is ordered. Steel is cut to length and it does not stretch.

06

The sequence after the shell is up

Roof and weathering-in, then windows and doors, and only then does the inside start: first-fix electrics and plumbing, insulation, boarding, plaster, screed or floor build-up, second-fix joinery, tiling, decoration, flooring, and finally the garden put back.

Every one of those has to follow the one before it, and every gap between them is a week added. This is the whole argument for one company with its own trades: the sequence is a programme rather than a negotiation between six firms’ diaries.

Worth knowing

Plaster needs to dry before it is decorated — properly dry, which in a cold month is a fortnight, not a weekend. Allow for it or pay for it later.

Next step

Bring us in before the drawings, not after them.

The cheapest hour you will ever spend on an extension is the one where a builder stands in the room and tells you what each option actually costs to build. Plenty of beautiful drawings get binned at tender stage for want of that conversation.